Our surveyors will work to ensure that the installation is carried out in line with good practice and that any testing is carried out as per the validation plan.

 

All our surveyors hold the NVQ Level 4 in gas membrane verification or the NVQ Level 2 in gas membrane installation.

 

Whilst all sites require an element of independent inspections, it is possible for some of the evidence required to be collated by the installers and main contractors under their own CQA. When this is the case we provide CQA site proformas to ensure the correct information is collated.

 

A Veification report is produced by us on completion of the full installation for submission to the local authority or warranty provider.

 

 

 

  • VISUAL INSPECTIONS
  • AIR LANCE TESTING
  • PROBE TESTING
  • ULTRASONIC THICKNESS TESTING
  • DIELECTRIC TESTING
  • TRACER GAS TESTING